A fully reconstructed highway delivered to council specification, completed during school holidays through careful planning and liaison, achieving on-time, on-budget delivery and formal adoption.

Project info

Client

Barratt Homes

Project Year

February 2023

Location

York, Yorkshire

About project

The Challenge

The project required full excavation of an ageing concrete carriageway while maintaining access to a live 400-unit residential development, an adjacent school, and an active bus route.

At the same time, an additional live JRHT construction site was operating within the same period, all accessed via a single shared entry point, requiring careful coordination and robust traffic management throughout.

The Solution

The scheme involved full reconstruction in accordance with York City Council highway specifications, with works carefully programmed during school holidays to minimise disruption.

Extensive upfront planning, detailed service identification, and proactive resident liaison ensured the works were delivered smoothly and efficiently.

The project was completed on time, within budget, and has since been formally adopted by York City Council.